Committee flags culvert shortfall after materials list and map differ
Jul 23, 2026
Jul 23, 2026
The committee found a discrepancy between the materials list (12 culverts) and map markings (7 culvert locations). Members discussed buying extra culverts now to avoid rework later and agreed to revisit the materials list with the contractor.
The full story
Committee members reviewed the plan and materials list and found a mismatch: the supplies sheet lists 12 culverts while plan markings show only seven locations. Members worried a shortage could force later rework if the contractor must improvise with cut pieces.