Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Track paving, science-lab and HVAC work progressing on referendum projects, board told
Summary
Administrators reported construction progress: track blacktop installation imminent, science labs have epoxy floors and cabinets installed, and elementary HVAC/temporary wall replacement is on schedule with a targeted early-August HVAC unit installation.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District administrators updated the board on ongoing referendum-funded projects, including the high-school/middle-school track and science-lab renovations.
The district reported that track crews were expected to place blacktop within days, followed by a 30-day curing period before surfacing and painting; administrators said they expect substantial completion in time for early football games though final painting may continue. Science labs at the middle and high school have epoxy floors and new cabinets in place, and elementary work is in drywall and painting stages. The district noted the new HVAC unit installation is scheduled for about Aug. 8 and that staff may briefly close the daycare while a crane places the unit.
Board members were invited to tour the projects after the meeting; administrators said custodial staff assembled tables and saved the district money during the renovation work.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

