Citizen Portal

Get email alerts on the Utilities Electrical Conversion topic

No spam. Unsubscribe anytime.

City receives electrical conversion schedule; construction start dependent on materials

Larned City Council · February 2, 2026

Summary

City Manager Bradley Eilts relayed a project schedule for the Electrical Conversion work based on information from Utility Help Net, including design and procurement milestones (maps and staking sheets 2/27/26; material list 3/10/26), bid reviews in March–April and a target contract award on May 4, 2026; construction timing depends on materials availability.

City Manager Bradley Eilts updated the Larned City Council on the Electrical Conversion project Feb. 2, relaying dates and milestones provided by Cris Neagle of Utility Help Net.

The timeline presented includes completion of preliminary and detail design tasks and project maps and staking sheets on Feb. 27, 2026; issuance of the material list on March 10, 2026; procurement reviews and bid evaluations through March and April; and a planned contract award on May 4, 2026. Eilts emphasized that a construction start date will depend on materials availability.

Councilmember Rusty McClendon said he will remain in contact with Cris Neagle to continue moving the project forward. Staff will proceed with the procurement and contracting steps outlined in the presented schedule.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source