Engineers report Forest Service grant progress; FEMA award delayed and extension requested
Aug 13, 2025
Forsgren Associates reported phase one of the Forest Service grant work should finish by September; a pay application and a small change order were presented. FEMA issued a notice of award to Reeder Excavating but is delaying review; the city engineer requested an extension of the spending deadline to Nov. 3.
The full story
Forsgren Associates' Camille Miller told the council that phase one of the Forest Service grant work is expected to be complete by the end of September and presented a pay application to RS Jobber for $83,268.66. Miller also presented a $4,000.94 change order tied to revising a sprinkling/grass plan; she said grant funds would cover that change order.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →