Engineering reports progress on Phase IV sewer work; Phase V on hold

Aug 27, 2024

The town’s engineering update noted Phase IV construction progress and a pending environmental clearance to add three customers near Sandy’s Hardware, Phase V is on hold, Route 20 Corridor permit modification is underway, AML Phase I closeout and Change Order #3 expected, and Phase II NEPA assessment has been drafted.

The full story

Ryan Holcomb delivered the engineering report at the Aug. 27 meeting, saying the Phase IV sewer project held its first construction progress meeting and that staff are working to add three customers near Sandy’s Hardware to the contract pending environmental clearance and DEP approval. He reported Phase V of the sewer project is on hold for the time being.