County approves pay request for courthouse renovation as shoring removed
Jul 7, 2026
Jul 7, 2026
Supervisors approved Turner Construction pay application for courthouse renovation work; contractors reported structural reinforcement complete and shoring removal underway on level three, with interior finishes and sod installation advancing.
The full story
The Dallas County Board voted July 7 to approve a pay application for work on the courthouse renovation as crews proceed with shoring removal and interior finishes.