County engineer briefed commissioners on Community Crossings projects, bridge milestones and an on-site bid opening that returned three roofing bids; board moved to take the bids under review.
The full story
The county engineer (agency official) reported completion milestones for Community Crossings 2025 work in multiple areas and provided updates on current bridge projects, including Bridge 69 where piling work progresses and Bridge 134 which is behind schedule due to an active utility line.