County staff outline December training and February 2025 target for new CAD/RMS system, warn data-conversion risks
Sep 10, 2024
Sep 10, 2024
Staff said functional acceptance testing for the new CAD is complete and training is slated for late November–December, with a mock go-live in January and a target go-live in February 2025, but warned data conversion from Tyler and TLITS/TLETs interfaces are medium-to-high risks that could delay the schedule.
The full story
County project staff gave a technical update on the 365 Labs Computer Aided Dispatch (CAD) and Records Management System (RMS) project and outlined a timetable and risk points for implementation.