Board approves final payments on three highway contracts, accepting completed work
Feb 17, 2026
Lincoln County accepted completion of three highway contracts and authorized final payments to A&C Excavating and Midwest Contracting; the resolutions list contract amounts and final payment totals.
The full story
Lincoln County Highway Engineer Joe Wilson presented three separate final-payment resolutions to accept completed highway and culvert projects and authorize final payments.
Resolution 11-2026 accepted completion of Contract 01-2023 Township Box Culverts by A&C Excavating with original contract amount $881,202.19, contract changes $350.00, revised contract $881,552.19, final contract $845,857.37 and final payment $9,848.23. Resolution 12-2026 accepted Contract 02-2024 Culvert Replacement by A&C Excavating with original $773,758.37, changes $9,707.00, revised $783,465.37, final $708,414.00 and final payment $5,440.74. Resolution 13-2026 accepted Contract 01-2025 Box Culvert on County Highway 8 by Midwest Contracting with original $489,018.86, final contract $477,426.90 and final payment $5,450.98. Each resolution was approved with a recorded 4-0 vote.
Written with AI from the event video and transcript. Check it against the source ↓