The Board accepted completion of Contract 02‑2023 (box culvert) by R&G Construction and authorized final payment; final contract amount was $776,162.58 and final payment $8,529.23.
The full story
County Highway Engineer Joe Wilson presented Resolution 37‑2025 accepting the completed box culvert construction under Contract 02‑2023 by R&G Construction. The resolution reported contract figures: original contract $773,283.50; contract changes $(250.00); revised contract $773,033.50; final contract amount $776,162.58; and final payment amount $8,529.23.