Board accepts completed box‑culvert project and authorizes final $8,529 payment to R&G Construction

Nov 18, 2025

The Board accepted completion of Contract 02‑2023 (box culvert) by R&G Construction and authorized final payment; final contract amount was $776,162.58 and final payment $8,529.23.

The full story

County Highway Engineer Joe Wilson presented Resolution 37‑2025 accepting the completed box culvert construction under Contract 02‑2023 by R&G Construction. The resolution reported contract figures: original contract $773,283.50; contract changes $(250.00); revised contract $773,033.50; final contract amount $776,162.58; and final payment amount $8,529.23.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in