Citizen Portal

Get email alerts on the Construction topic

No spam. Unsubscribe anytime.

Project manager outlines construction schedule and septic options; start targeted for Oct. 13

Middletown Springs Library Trustees · September 25, 2025

Summary

Peter Stevenson said Naylor expects to start on-site October 13; Doren Brothers will locate the septic and the proposed modified mound system would permit roughly 50 seats (plus 25 ancillary), with an estimated cost of $30,000–$60,000 pending final design and bids.

Peter Stevenson, speaking for the town's construction team, summarized progress with the contractor Naylor and said the project is moving toward on-site work. "They're expecting to start October 13," he said, and noted that shop drawings remain in progress but most items are done and approved.

Stevenson described septic work: Doren Brothers will visit to locate the septic tank (initial visit $175), with follow-up services priced by task and an anticipated modified mound system permitable for about 50 seats with provisions for approximately 25 ancillary occupants. He said the septic buildout could be in the range of "anywhere from 30 to $60,000" but that a formal design and bids will be necessary to determine final cost.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source