Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Grindstone repairs near completion; tower punch list and interducting work underway

TV District Board · November 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board received updates that Grindstone road grading and drainage are complete for the season, a waveguide pump failure was repaired, insurance adjustments for lightning damage are pending, interducting for six 6‑inch conduits was completed to improve cable management, and only final tower ladder and punch‑list items remain.

Operations staff and contractors told the board repair work at Grindstone has reduced outages and improved access but weather stopped parts of the project for the season. On technical failures, the waveguide transmission line pump and dehydrator at Lamoille failed and were repaired, and crews completed ground work including drainage ditches and gravel where needed. "We did have 1 item failure that needed immediate attention is a waveguide transmission line pump and dehydrator. That work is completed," the operations speaker said.

Staff also described an interducting installation of six 6‑inch conduits to organize customer and district lines (quoted at about $13,000). The contractor punch list for the new tower includes permits, engineering as‑built documents, soil surveys and grouting of anchor bolts; only the last 40 feet of the waveguide ladder remains before the tower closeout, and fieldwork will resume as soon as weather permits.