Engineer outlines timelines for three Vernon County bridge projects
Summary
Great River Engineering reported bid and completion windows for three county bridge projects, including BRO-R108(001) over the Marmaton River with bids expected March–April 2025 and completion anticipated March–April 2026.
Get email alerts on the Bridge Projects topic
No spam. Unsubscribe anytime.
Lindsey Chaffin of Great River Engineering updated the Vernon County Commission on the status of three county bridge projects, giving projected bid and completion windows and reporting construction progress.
Chaffin said BRO-R108(001), the Marmaton River bridge in Compton Junction, should be ready to open bids in March or April 2025 with anticipated completion in March or April 2026. She also reported BRO-R108(45), the Springer Bridge, should be ready to open bids in January 2025, and that construction on BRO-R108(46), the Hinkle Bridge, is progressing. The update gives county staff scheduling markers for procurement and traffic planning ahead of construction.