Village engineer reports Cambridge Boulevard survey complete; hydrant testing and GIS work underway

Jan 21, 2025

Village Engineer Caleb Zmith told council the Cambridge Boulevard survey is complete and a 30% plan should be ready in March; hydrant testing is complete with calibration in progress and the GIS system expected online in the coming months.

The full story

Village Engineer Caleb Zmith reported that the Cambridge Boulevard survey has been completed and he expects a 30% plan to be ready in March. He also reported that hydrant testing is finished and calibration is now taking place.