Commissioners approve change orders to complete Rattlesnake water lab

Jan 27, 2026

Fayette County approved Change Orders #1 and #2 for the Rattlesnake Water System Improvements (Contract A), adding $6,126.48 to finish the permanent laboratory—bringing that contract to $100,662.58.

The full story

The Fayette County Board of Commissioners voted January 27 to accept Change Orders #1 and #2 for the Rattlesnake Water System Improvements (Contract A) after a request from Crystal Corbin, the county's program manager. The revisions adjust the size of a chase pipe and add a fume hood necessary to complete the permanent laboratory; the change orders increase the contract by $6,126.48 to a new total of $100,662.58.