Committee reviews 12‑month moratorium and new definitions for data centers

St. Croix County Community Development Committee · July 9, 2026

Summary

Committee members reviewed a proposed 12‑month moratorium on medium and large data centers and new size-based definitions (small <500 kW; medium 500 kW–10 MW), with concerns raised about cooling, water use, noise and measurement challenges for small businesses.

Staff recommended a 12‑month moratorium on medium and large data centers while the county refines definitions and performance standards; the draft definitions would exempt small, in‑house server rooms (under 500 kilowatts) but cover containerized or purpose-built facilities that consume larger amounts of power.

Supervisors and members of the public raised concerns about cooling systems, noise, and water use for larger facilities and noted practical challenges for small businesses in reporting power usage. Staff said the moratorium text came from corporate counsel and that definitions will likely be revised after outreach to associations and legal review. “The moratorium shall be in effect for a period of 12 months,” staff said; committee members asked staff to bring town association feedback back to the August meeting.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source