Commissioners authorize adding $85,000 for jail design and development in planning discussion
Summary
County staff estimated architectural design and development for a proposed jail expansion could be about 10% of final construction cost, suggesting an $85,000 design allocation in FY26 to begin planning for a projected multi-million-dollar project.
Get email alerts on the Jail Expansion topic
No spam. Unsubscribe anytime.
Rodney, a county staffer involved in facilities planning, told the court initial architectural and design work commonly runs about 10% of the final project and estimated design-and-development work for a proposed jail expansion at roughly $85,000.
"Your architecture was just your design and development. He's gonna come in for $8,085,000 and give you the initial design," Rodney said, and later clarified the 10% rule-of-thumb. Commissioners discussed whether to include the $85,000 in FY26 and how to fund the larger construction when the time comes, noting that design work can proceed even if construction is several years out. The court agreed to add the design figure to begin planning and requested more detailed cost modeling from the architect as the next step.