Brooklyn drainage project winding down; about 30 mailboxes to be fixed case‑by‑case

Apr 13, 2026

Jamieson told the committee the Brooklyn phase 1 paving is nearly complete with three pours remaining and substantial completion expected in the next 8–10 weeks; approximately 30 damaged mailboxes will be addressed individually with homeowners.

The full story

Jamieson updated the committee that the Brooklyn drainage and paving work is "winding down." He said the contractor is anticipating substantial completion late May but he would "probably say we're looking closer to mid to late June," and that the primary paving task has about three pours remaining before second‑stage work (sidewalks, sod, manhole and junction box cleanup) begins.