Hinkle Bridge work slowed by weather; change order signed to extend construction to March 3

Jan 22, 2025

Great River Engineering reported delays on Hinkle Bridge (BRO-R108(46)) due to holidays and cold weather; the Commission signed a change order to be approved by MoDOT extending construction with a March 3 completion date.

The full story

Jake McBee of Great River Engineering told the Commission that work on the Hinkle Bridge project (BRO-R108(46)) has slowed because of recent holidays and cold weather. Presiding Commissioner Joe Wilson signed a change order that will be submitted to the Missouri Department of Transportation (MoDOT) to extend the construction timeline; the minutes record a new completion date of March 3.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in