Hinkle Bridge work slowed by weather; change order signed to extend construction to March 3
Jan 22, 2025
Great River Engineering reported delays on Hinkle Bridge (BRO-R108(46)) due to holidays and cold weather; the Commission signed a change order to be approved by MoDOT extending construction with a March 3 completion date.
The full story
Jake McBee of Great River Engineering told the Commission that work on the Hinkle Bridge project (BRO-R108(46)) has slowed because of recent holidays and cold weather. Presiding Commissioner Joe Wilson signed a change order that will be submitted to the Missouri Department of Transportation (MoDOT) to extend the construction timeline; the minutes record a new completion date of March 3.