Commissioners accept Cedar Creek Trail segments after change orders; middle segment increased, west finalized under budget
Jan 30, 2026
Jan 30, 2026
Allen County approved change orders and final acceptances for Cedar Creek Trail west and middle segments. The west segment netted an $11,005.47 decrease and a final amount of $792,645.53; the middle segment increased by $97,824.06 but remained under the engineer's estimate with a final amount of $1,604,925.09.
The full story
Allen County Highway Director Bill Hartman presented change orders and final acceptances for segments of the Cedar Creek Trail. The west segment's final change order with API Construction Corp. resulted in an $11,005.47 decrease after removal of concrete curbing to improve surface runoff; the board accepted the west segment project for a final amount of $792,645.53.