Commissioners approve $13,792.55 reduction to Rocky Ridge Road Bridge contract

Board of Ottawa County Commissioners · February 10, 2026

Summary

Change Order No. 2 with R&I Construction, Inc. was approved, reducing the Rocky Ridge Road Bridge contract by $13,792.55 to a new total of $933,718.75 to reconcile final quantities; the County Engineer recommended the change and the Prosecuting Attorney approved it.

The Board authorized Change Order No. 2 with R&I Construction, Inc., for the Rocky Ridge Road Bridge project. The change order reduces the contract by $13,792.55 to reconcile final quantities, bringing the new contract price to $933,718.75. The County Engineer recommended the adjustment and the Prosecuting Attorney approved the action.

The motion was moved by Commissioner Donald A. Douglas and seconded by Commissioner Mark E. Coppeler; Commissioners Mark W. Stahl, Donald A. Douglas and Mark E. Coppeler voted yes. The record does not indicate that the change order affects the project completion date or other contractors.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source