County to use lower-cost 'Select Fill' for multiple road edging projects

Clay County Board of Commissioners · March 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After reviewing bids, the Board directed the Highway Administrator to use the lower‑cost Select Fill material for edging three blacktop road projects with combined Select Fill estimates of about $65,651.25.

Highway Administrator Bobby Shomper presented cost comparisons for edging blacktop roads and the Board directed staff to use the lower-cost Select Fill option at the March 23 meeting.

Listed estimates included: Frontier Road (Hwy 24 to Clifton) — Select Fill $37,800 vs AB3 $123,120; 23rd Rd. & Frontier Rd. to Morganville River Bridge — Select Fill $4,226.25 vs AB3 $13,765.50; Redwood Rd., 9th Rd. & Sunflower Rd. (8 miles) — Select Fill $23,625 vs AB3 $76,950. Commissioners instructed Shomper to proceed with Select Fill for the identified sections.