Cowley County commissioners approved a required NEPA study addendum costing $78,000 to meet federal grant compliance and authorized advancing the Bridge Improvement Project with a total project cost not to exceed $908,000.

The full story

Public Works Superintendent Jon Jordan informed the board that a NEPA (National Environmental Policy Act) study addendum is required for federal compliance on the Bridge Improvement Project, and that the addendum would cost $78,000. Commissioners approved proceeding with the NEPA study and authorized advancing the project with a total project cost not to exceed $908,000; Vice Chairman Jim Maxwell moved and Commissioner Alan Groom seconded the motion, which passed 3-0.