JC Park work progresses; summer program reports 10% participation increase

Jul 27, 2026

Contractors have resumed work at JC Park: playground fencing is complete, parking prep and sidewalk pouring are underway, and restrooms remain two to three weeks out; staff also reported the summer parks program had about a 10% increase in participation and raised roughly $1,820 at a fundraiser.

The full story

Staff reported contractors are back at JC Park: the kitty fence around the playground is complete, crews are preparing parking and the sidewalk is expected to be poured; the bathroom contractor remains two to three weeks away. Staff said they will close off the bathroom area so the park can safely open while finishing work continues.