Premier Lakes reports minor algae, corrected aeration and back-ordered equipment

Jan 28, 2025

Premier Lakes reported minimal red algae to be treated, most aeration units corrected with two needing electrical work, and a back-ordered "Zombie box" scheduled for installation in three weeks; staff will seek littoral replanting costs behind 20859 Glen Eagles Lakes Drive.

The full story

Dustin Hormann of Premier Lakes told the Board that crews "identified minimal red algae in the lakes, which will be treated tomorrow," and that recently treated dry-retention areas and corrected aeration issues left two units requiring electrical work next week. He said a back-ordered "Zombie box" will be installed at the Masters in three weeks.

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in