Premier Lakes reports minor algae, corrected aeration and back-ordered equipment
Jan 28, 2025
Premier Lakes reported minimal red algae to be treated, most aeration units corrected with two needing electrical work, and a back-ordered "Zombie box" scheduled for installation in three weeks; staff will seek littoral replanting costs behind 20859 Glen Eagles Lakes Drive.
The full story
Dustin Hormann of Premier Lakes told the Board that crews "identified minimal red algae in the lakes, which will be treated tomorrow," and that recently treated dry-retention areas and corrected aeration issues left two units requiring electrical work next week. He said a back-ordered "Zombie box" will be installed at the Masters in three weeks.
Sign up to keep reading.