Get email alerts on the Detention Hvac topic
No spam. Unsubscribe anytime.
Butler County moves forward on phased HVAC replacement at Detention Center
Summary
Facilities Management told commissioners the detention center’s rooftop units and energy recovery ventilators are failing and will be replaced in phases; the Board approved a contract with Innovative Groups to begin the next phase of RTU and control replacements.
Get email alerts on the Detention Hvac topic
No spam. Unsubscribe anytime.
Travis Cornell, Butler County Facilities Management Director, told the Board the detention center’s rooftop units (RTUs) and energy recovery ventilators (ERVs) "are beginning to fail and are in need of replacement," and outlined a plan to replace several units each year until all units are renewed. He said the work is part of an ongoing HVAC replacement program intended to spread replacements over multiple fiscal years.
Commissioner Darren Jackson moved to authorize the Innovative Groups contract for RTU replacement and controls at the Detention Center; Commissioner Kelly Herzet seconded the motion and it carried 5-0. The Board did not specify contract dollar amounts in the verbal record provided at the meeting.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.
