Road & Bridge reports dust-control, bridge work and a $143,330 deficit on W Road project

May 18, 2026

Road and Bridge Superintendent Joe Gardner told the Board crews began residential dust control and that the rock budget is $438,907.19 while the W Road project shows a negative balance of $143,330.40; hauling has paused due to budget constraints and crews are addressing equipment repairs.

The full story

Road and Bridge Superintendent Joe Gardner presented his weekly update on May 18, telling the Board crews began residential dust control last Friday and previously completed county roads. Gardner said a resident asked about building a home off 94th Road and the county verified that portion of the road is maintained by Rossville Township/Shawnee County.