Summary

Commissioners approved Work Change Directive No. 1 for Contract A at the Rattlesnake Water Treatment Plant to replace a Franklin Electric pump with an ABB 240V 1‑phase 5HP VFD (adjustment to Contract A: $27,706.90; total cost increase $26,450.50; CMAR fee $1,256.40).

The Fayette County Board of Commissioners authorized Work Change Directive No. 1 for Contract A at the Rattlesnake Water Treatment Plant on Feb. 17, 2026. The directive, recommended by Verdantas/CT Consultant and submitted by Bowen Engineering, calls for replacing a Franklin Electric Model 30VRL-05-2Astg-3HP vertical stage pump with an ABB 240V 1‑phase drive 5HP pump and performing necessary wiring updates to support the 5HP VFD.

The minutes record an adjustment to Contract A in the amount of $27,706.90, a stated total cost increase of $26,450.50, and a CMAR fee of $1,256.40 (4.75%). Commissioner Donald L. Fleak moved to authorize the change directive and Commissioner James D. Garland seconded; the motion carried on roll call (all aye). Documents and the directive are on file with the county.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source