County updates artificial reefs phase 2; deployment expected in late August
Jul 7, 2026
Shelley Alexander (environmental department) said phase 2 planning is complete: 128 limestone modules and ledge/disk modules will create 25 patch reefs about 4 miles southeast of Pensacola Pass. FWC contract FWC 21366 was extended to December 2026 and construction extended to Nov. 3.
The full story
Shelley Alexander of the county environmental department described the phase 2 artificial reefs plan: structural modules (including 128 eight-foot limestone modules and additional ledge and disk modules) will form 25 patch reefs within the Escambia East nearshore artificial reef site roughly four miles southeast of Pensacola Pass.