Committee approves $27,115 extra for lightning protection after original allowance proved insufficient
Summary
Pierce County approved COR#12 Dec. 11 to revise the lightning protection plan; an additional $27,115 will be paid from owner’s contingency after the initial $50,000 allowance was determined inadequate.
Get email alerts on the Safety topic
No spam. Unsubscribe anytime.
Committee members approved Change Order Request COR#12 after Market & Johnson representative John Nuzum told the committee that lightning protection had not been fully designed at bid and the $50,000 allowance was insufficient. The county will use its current contractor for the work and the additional cost is $27,115 from owner’s contingency within Market & Johnson’s contract.
The motion (moved by N. Gulbranson, seconded by S. Bjork) carried unanimously. Committee members accepted the use of the county’s contractor and recorded that the allowance shortfall required a contingency draw; no alternative funding source was identified in the minutes.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.