County approves HDR engineering amendment for CR4 pole relocation; signs CR3 construction contract

Jan 6, 2026

The board approved a $57,080 amendment to HDR Engineering for the CR4 improvement project (total engineering cost now $1,036,778.29) with costs split 50/50 with Mountrail Williams Electric Cooperative, and approved a construction agreement and Notice to Proceed for Palermo North CR3 Project No. 03(71)23 with Jensen Brothers Construction.

The full story

At 9:50 A.M. the board heard a presentation from Road & Bridge Engineer Jana Hennessy on several transportation projects.