Contractor and select board members discussed State and USACE permitting, traffic control (one‑way alternating flows for about 10 weeks) and guardrail reuse for Stratton Access Road culvert work; Hunter Excavating will revise design sketches for permitting.

The full story

During the July 10 emergency meeting, Hunter Excavating and Select Board members detailed the permitting and traffic control requirements for the Stratton Access Road culvert work. The contractor said both Culverts #42 and #43 will require State and U.S. Army Corps of Engineers (USACE) permits; permanent and temporary impacts will determine which permits and how long processing will take.