Assistant county engineer reports Winslow Road bridge work, seal coat completion and culvert stabilization
Summary
Assistant county engineer Brian Brennan told the board the Winslow Road bridge has largely been removed and bridge crew plans to set a deck soon; seal coat work finished and grout stabilization around culverts was completed yesterday.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Brian Brennan, assistant county engineer, briefed the Board on multiple road and bridge projects underway across the county.
"Our Winslow Road Bridal project does continue. They do have the bridge removed, for the most part at this point," Brennan said, adding the bridge crew expects to set a deck on Off Road in the coming week and that the seal coat project had just finished. He also reported Denco completed grout stabilization around culverts and that dust control crews are preparing a second round of spot treatments.
No formal action was required; the update was accepted as routine project reporting.