Commission rescinds Feb. work directive and approves pump and control upgrades at Rattlesnake Water Treatment Plant

Fayette County Board of Commissioners · March 2, 2026

Summary

The board rescinded a Feb. 17 work change directive and approved Work Change Directive No. 1 for Contract A at the Rattlesnake Water Treatment Plant, adding pump and variable-frequency-drive upgrades; total cost increase $26,450.50, CMAR fee $1,256.40.

At the March 2 meeting, the Fayette County commissioners moved to rescind a February 17, 2026 work change directive and to authorize Work Change Directive No. 1 for Contract A at the Rattlesnake Water Treatment Plant. The directive adds replacement of a pump (Franklin Electric Model 30VRL-05-2Astg-3HP vertical stage unit), replacement of a control panel (from Eaton AN19BN0A5E020 to an ABB 240‑Volt, 1‑Phase, 5HP drive) and any necessary wiring updates to support a 5HP variable-frequency drive.

The minutes record an adjustment to Contract A sum of $27,706.90 and a total cost increase of $26,450.50; the Construction Manager at Risk (CMAR) fee at 4.75% is $1,256.40. The motion to rescind and replace the directive carried with Commissioner Garland absent.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source