Montgomery County authorizes water main replacements and advances AMI planning
Mar 24, 2026
The Board awarded construction contracts for Drexel Park and East Orchard Springs water main replacements totaling $1,976,353 and authorized procurement steps for Advanced Metering Infrastructure Phase II and related solid-waste stormwater improvements.
The full story
The Board authorized construction agreements with C.G. Construction & Utilities, Inc. for Drexel Park water main replacement Phase 1 at a low bid of $713,148.00 (project term to Dec. 31, 2027) and East Orchard Springs water main replacement at $1,263,205.00 (project term to Dec. 31, 2027). Both were listed as the lowest and best bids for their respective projects.