Board accepts $133,271 GMP amendment to replace lagoon slide gates with weir gates
Mar 9, 2026
Fayette County accepted a Guaranteed Maximum Price amendment to replace slide gates with weir gates at lagoons, adding $133,270.92 in costs; installation is scheduled to be completed by July 1, 2026.
The full story
The Fayette County Board of Commissioners accepted an amended Guaranteed Maximum Price (GMP) amendment from Bowen Engineering Corporation on March 9 to replace slide gates at wastewater treatment lagoons with weir gates. The minutes record construction cost of $123,399.00, CMAR fee of $5,864.45, and contingency $4,010.47 for a total change order cost of $133,270.92. Work is scheduled for completion by July 1, 2026.