Public Works reports bridge progress and recent hires
Summary
Public Works reported tree trimming and sign repairs, said the Osage Trail bridge has 27 days until completion and confirmed the hiring of Kylie Bougher for the Road Department.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Don Sanders, representing Public Works, told commissioners the department has completed tree trimming and sign repairs in recent weeks and that the Osage Trail bridge project has 27 days remaining until completion. Sanders also reported that Kylie Bougher was hired for the Road Department and that the Noxious Weed Department has equipment at Prairieland for repairs.
"The Osage Trail bridge has 27 days left until completion," Sanders said. Sanders noted HVAC problems were addressed and technicians will return when weather permits to check lines. The board received the update with no recorded dissent.