County awards resurfacing contract; structure replacement to precede paving on Wabash Road

Miami County Council · April 21, 2026

Summary

Miami County reported a combined plan: E&B Paving bid $1,099,741 for resurfacing Wabash Road and Paw Paw Pike with CCMG funding covering $879,792.80 (80%) and a local balance of $219,948.20; a separate structure replacement estimated at $711,764 will be completed first, with overall completion expected by late November 2026.

County planning staff updated the council on CCMG-funded resurfacing and a separate structure replacement on Wabash Road.

Janice Hughes said E&B Paving's combined resurfacing bid totaled $1,099,741; the CCMG award is $879,792.80 (80%), leaving a local match of $219,948.20. A separate, non-CCMG structure replacement on Wabash Road is estimated at $711,764 and will use local/LPA funds. Hughes noted the highway department’s combined local spend for the projects is $931,622.20. The sequence will replace the structure first (targeted completion in October 2026), followed by paving, with overall work expected to finish by late November 2026.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source