Commission debates noise limits and backup-generator limits for data centers

Apr 30, 2026

Robert Busby urged a lower noise standard — 50–55 dB at the property line — and commissioners discussed restricting backup generators to emergency power and capping annual runtime; language from Busby's Section 13.9 was proposed to be added to Section 9.5.3.

The full story

The Planning Commission debated acceptable noise limits for data centers and how to regulate backup power. Secretary Robert Busby said 65 dB at the property line was too high and suggested a 50–55 dB limit, and the commission discussed adding generator restrictions that would limit runtime and bar generators from serving as the primary power source.