Outer Loop schematics submitted; Horizon Road design work advances toward summer public hearing

Infrastructure Consortium · June 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The consortium was told the 95% schematic for Outer Loop Phase 1 was submitted June 5 and that Bridgefarmer has begun layout and traffic analysis for Horizon Road; a public hearing for the Outer Loop is anticipated in summer 2026.

Erica reported the Outer Loop Phase 1 95% schematic (including ICE, cost and hydraulic reports) was submitted June 5 and that evaluation of alternatives for Phase 2 continues. She said bimonthly coordination with TxDOT and monthly coordination with COG are ongoing and that the county has been resolving environmental assessment comments in preparation for a public hearing expected in summer 2026.

On Horizon Road, Bridgefarmer has developed exhibit layouts showing both four‑lane and six‑lane configurations, identified preliminary right‑of‑way limits and started traffic and crash‑data analysis. A staff member said the consultant arrived well prepared for the kickoff meeting and the county will continue design and public outreach work ahead of the summer hearing.