Engineers report data complete for US‑278/Argent projects; public meetings set for October

Jul 22, 2026

Engineers said surveying, LIDAR, traffic counts and traffic modeling are complete for US‑278 and Argent Boulevard; they favor widening to the outside where feasible, expect signal changes to alter counts by early 2027, and plan public information meetings in the first week of October.

The full story

Jeff Buckley, the project presenter, said the US‑278 and Argent Boulevard projects are in preliminary engineering and planning. "All that data is collected and done," Buckley said, listing field control surveying, LIDAR and updated traffic counts. He added that utility coordination and environmental flagging are underway.