Premier Lakes reports minimal red algae, aeration fixes; installation delayed by back order

Jan 28, 2025

Premier Lakes staff told the board crews found minimal red algae to be treated, corrected most aeration issues with two units pending electrical work, and said a 'Zombie box' installation at the Masters is delayed three weeks due to a back order. A request was made for littoral replanting behind 20859 Glen Eagles Lakes Drive.

The full story

Dustin Hormann of Premier Lakes told the River Ridge board that "Crews identified minimal red algae in the lakes, which will be treated tomorrow," and that dry retention areas had recently been treated. He reported aeration issues were corrected except for two units that require electrical work scheduled for the next Monday or Tuesday.