Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Public Works facility near completion stages; bond spending reported
Summary
City staff reported construction progress on the new Public Works facility: vehicle storage insulation is complete, material storage metalwork is in progress, near‑term tasks scheduled, and $2,113,969.54 of the $9,000,000 bond has been paid to date (23%). Completion is scheduled for August 2025.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City Manager David Larson provided an update on the Public Works facility at 104 East South Weber Drive being constructed by Valley Design and Construction, Inc. He reported that insulation for the vehicle storage building is 100% complete and the metal section of the material storage building is under construction; near‑term tasks include a floor drain, masonry work and rain gutter storage system installation.
Larson told the council the project is scheduled for completion in August 2025 and that bond payments to date total $2,113,969.54 of $9,000,000, or 23 percent. Staff will continue to provide progress reports and the council noted the timeline and remaining budget as the project advances.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.
