Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Public Works facility near completion stages; bond spending reported

South Weber City Council · February 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported construction progress on the new Public Works facility: vehicle storage insulation is complete, material storage metalwork is in progress, near‑term tasks scheduled, and $2,113,969.54 of the $9,000,000 bond has been paid to date (23%). Completion is scheduled for August 2025.

City Manager David Larson provided an update on the Public Works facility at 104 East South Weber Drive being constructed by Valley Design and Construction, Inc. He reported that insulation for the vehicle storage building is 100% complete and the metal section of the material storage building is under construction; near‑term tasks include a floor drain, masonry work and rain gutter storage system installation.

Larson told the council the project is scheduled for completion in August 2025 and that bond payments to date total $2,113,969.54 of $9,000,000, or 23 percent. Staff will continue to provide progress reports and the council noted the timeline and remaining budget as the project advances.