County approves about $5,000 in change orders for courthouse project
Summary
Marshall County approved four change orders for the courthouse OPN Architects/Garling Construction contract totaling several thousand dollars for sealing, hydrant removal, access panels and ceiling scope changes; Buildings and Grounds Director said the net increase remains within the project budget.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Marshall County Board of Supervisors approved Contract Change Orders #3–#6 for the county courthouse project on April 22, covering a Dow 758 primary seal ($1,669.50), removal of a hydrant ($726.37), two 24x36 access panels with detention deadlocks ($1,363.79), and deletion and reinstallation of ceiling work in several rooms (net $4,724.43). Motions for each change order were moved and seconded and carried 3-0.
Lucas Baedke, Marshall County Buildings and Grounds Director, told the board the total increase from the change orders approved at the meeting added about $5,000 to the project and falls within the approved project budget. The board authorized the chair to sign the change orders.