Board authorizes $6,500 valve fix on Bear Creek South; multiple bridge projects underway

Board of Mayor and Aldermen of the City of Henderson, Tennessee · November 14, 2024

Summary

Utility Director Darryl Green received authorization to install a valve to fix a pressure issue on Bear Creek South (approx. $6,500). Green also updated the board that pre-construction work has begun on several TDOT bridge projects, including Hwy 100 and Dry Creek.

The board authorized Utility Director Darryl Green to proceed with a valve installation to correct a pressure issue caused by an elevation difference on Bear Creek South at an estimated cost of about $6,500. Ald. Keith Smith moved to authorize the work and Ald. Donna R. Butler seconded; the motion carried.

Green also reported that pre-construction or construction has started on multiple bridge projects—Hwy 100 and Dry Creek among them—and that pre-construction work for the Talley Store Road bridge began while the city monitors another bridge in the Montezuma area. Green acknowledged the Tennessee Department of Transportation’s involvement on several projects and thanked Assistant CMFO Alicia Holder for managing accounting on the work.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source