County engineer reports progress on Rockford Shop, bridge designs and 130th Street work

Feb 24, 2026

Adam Miller said interior work at the Rockford Shop is complete, culvert construction is being prepared with most forms received, closed bridges on 130th Street were removed, and a surveyor will be brought in to continue a road‑vacation process; recent heavy snowfall also created snow‑removal challenges.

The full story

Adam Miller, Floyd County Engineer, told the board that interior work at the Rockford Shop has been completed and that preparations for culvert construction are underway with most forms now received. He reported that closed bridges on 130th Street have been removed and a surveyor will be engaged to continue a road‑vacation process.