County engineer reports progress on Rockford Shop, bridge designs and 130th Street work
Feb 24, 2026
Adam Miller said interior work at the Rockford Shop is complete, culvert construction is being prepared with most forms received, closed bridges on 130th Street were removed, and a surveyor will be brought in to continue a road‑vacation process; recent heavy snowfall also created snow‑removal challenges.
The full story
Adam Miller, Floyd County Engineer, told the board that interior work at the Rockford Shop has been completed and that preparations for culvert construction are underway with most forms now received. He reported that closed bridges on 130th Street have been removed and a surveyor will be engaged to continue a road‑vacation process.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →