Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation topic

No spam. Unsubscribe anytime.

Ottawa Road paving underway; county targets end‑of‑August completion

Board of County Commissioners of Atchison County, Kansas · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor completed cement base and started asphalt paving on Ottawa Road; surface layers, rock shoulders, striping and seeding are scheduled next, with a target completion date at the end of August, county staff reported.

County staff and contractor Schwab Eaton updated commissioners on progress for Ottawa Road. The cement base was completed the week before last, crews began asphalt paving with the northbound lane finished, and crews planned the southbound lane base after a weather delay.

"The completion target date will be the end of August," the chair said after the update. Staff described a sequence of remaining work: surface layers for both lanes, rock shoulders next week, followed by striping and seeding. Commissioners said they were satisfied with progress and noted the contractor will inspect the Osborne Bridge approaches on both north and south sides as part of follow‑up work.