Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Board ratifies $150,786 change order for stormwater projects after debate on process
Summary
The River Ridge Board ratified MRI Construction Change Order Estimate #500 for Phase 1 and Phase II stormwater projects ($150,786.09) after debate about exceeding budget and the need for contingency rules; counsel was directed to draft 'ground rules' for project approvals above a threshold.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
District Engineer Charlie Krebs and PSGRC General Manager Eric Long explained that the MRI Change Order and relocated inlets for Phase II were driven by field conditions and homeowner input. Mr. Mountford said he believed approving "another $150,786.09 expense without scheduling a Special Meeting to discuss and vote on it" was not fiscally responsible, and raised concern that the CDD operation showed "major dysfunction" when approvals occur without additional board review.
Mr. Blumenthal acknowledged the timing issue, noting that projects delayed into FY2025 caused loan funds to be carried over, and moved to ratify the Change Order. The board directed District Counsel Tony Pires to draft "ground rules" to require a special meeting or set a contingency threshold for future approvals. On motion by Mr. Blumenthal and seconded by Mr. Merrill, the Board ratified MRI Construction, Inc. Change Order Estimate #500 for Price Changes of Phase 1 and Phase II Stormwater Management Projects in the amount of $150,786.09; the motion passed with all in favor.
The motion resolves an immediate procurement and construction funding item but prompted policy-level direction to develop clearer approval thresholds and contingency procedures for project managers and future change orders.
