Board limits Mayo River power easement; asks AEP to study alternate routing
May 11, 2026
May 11, 2026
Patrick County supervisors approved an Appalachian Power easement only at the Sheriff's Office parcel while asking the utility to study routing that avoids the Mayo River Rail Trail; AEP cited "rough terrain" and maintenance-access concerns and said build-out is planned for early 2027.
The full story
The Patrick County Board of Supervisors on May 11 approved a request from Appalachian Power (AEP) for easements tied to the Mayo River Station distribution upgrade, but limited immediate approval to the parcel at the Sheriff's Office while asking the utility to explore alternate routing that would avoid the Mayo River Rail Trail.